ORCHARD PARK, N.Y. — Construction of the new Buffalo Bills stadium is underway, and while it won't be done for another two years, there are some ways to chart the progress made in Orchard Park.
Work on fireproofing, masonry, overhead MEP infrastructure, and metal stud framing are all now underway.
Here's a look at the process, by the numbers, according to information from the team's Corporate and Stadium Communications office.
- 313 — That's the estimated miles of conduit that will be installed.
- 710 — That's how many workers were on site last week.
- 1,260 — That's the estimated miles of wire/cable that will be installed.
- 13,421 — That's how many pieces of steel have been installed.
- 15,952 — That's how many tons of steel have been installed.
- 23,514 — That's how many pieces of steel that will eventually be installed.
- 24,522 — That's how many tons of steel that will eventually be installed.
Canopy steel and deck installation is expected to start by the end of the month, a team spokesperson said. The targeted date for completion of the structural steel canopy is at the end of February, 2025.
The exterior face could be done in late March of 2025, the team said.